PMI-RMP PMI Risk Management Professional Practice Exam, Attend this PMI-RMP PMI Risk Management Professional Practice Exam will get a Good Score 80% on Main Exam.
Sample Questions
Q) There are five inputs to the quantitative analysis of the risk process. Which of the following is not an input to execute the process of quantitative analysis of the risk?
a) risk register
b) risk management plan
c) the cost management plan
d) Enterprise environmental factors
Q) Don has hired Jerry, a contractor, to complete a part of its project work. The contract was used a cost-plus contract. If Don were to perform a risk control, which would entail the risk in this scenario?
a) Don would be because it is the project manager.
b) Jerry would be due to the type of contract.
c) Don would be due to the type of contract.
d) Jerry would be because he is the contractor hired
Q) You are the project of BlueStar project manager in your company. Your business is structured as a functional organization and report to functional manager that you are ready to move on to the process of qualitative analysis of risk. What you need as input for the qualitative analysis of project risks in this scenario?
a) qualitative analysis of risks is through the project manager in a functional structure.
b) You will need to risk register, risk management plan, project scope, and any assets of the relevant organizational processes.
c) You will need to risk register, risk management plan, the outputs of qualitative analysis of risk, and any assets of the relevant organizational processes.
d) You will need to risk register, risk management plan, permission from the functional manager, and any assets of the relevant organizational processes.
Q) It works as a project manager for TechSoft Inc. is preparing to risk response plan for your project with the project team. How many risk responses are available for a positive risk event in the project?
a) Three
b) four
c) Seven
d) One
Q) Jeff works as a project manager for BlueWell Inc. He is determining which risks may affect the project. Which of the following are the inputs to identify risks that Jeff will use the process to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
a) Scope of the baseline
b) Activity of cost estimates
c) risk register
d) risk management plan